SpotWire

Five layers. One buildout. Different evidence.

October’s public documents show where physical AI capacity is being bought, connected, powered, housed, and financed. Each figure answers a different question.

Prepared · October source review

Reading rule. The figures below come from the named primary sources. They are not SpotWire index levels, completed-transaction prices, or a cross-market comparison. The latest published SpotWire collection dataset remains dated September 4, 2026. The October 30 internal collection is under source and coverage review, so this briefing does not publish its provisional levels or month-on-month changes.

The October evidence, by layer

The source, period, unit, and limit travel with each number.

Compute

$51.4B

Alphabet Q3 capital spending

Disclosed October 28

Company-wide quarterly capital expenditure, mostly technical infrastructure. It is not a GPU price or an industry total.

Read the primary source →

Interconnect

65%

Alphabet technical infrastructure allocation to servers and networking

Disclosed October 28

Share of one company’s technical infrastructure investment in Q3, not a networking-price index.

Read the primary source →

Power

5%

EIA estimate of Q3 2026 commercial electricity-use growth

Outlook released October 6

Year over year. The commercial category includes data centers and many other users. EIA also forecasts 2.8% growth in 2027; neither number is a data-center load estimate.

Read the primary source →

Facility

25 MW

ERCOT data-center information-request threshold

Responses due October 12

The request covered developers pursuing interconnection and asked about grid dependence, cooling, and water. It is not energized capacity.

Read the primary source →

Credit and debt · SWDI in development

6.78%

Lambda fixed rate on one $1.008B delayed-draw facility

Announced October 1

Issuer-reported terms for a GPU-backed financing. One structure cannot establish a representative credit index level.

Read the primary source →

What the numbers can and cannot say

Alphabet’s spending and allocation show the scale and composition of one hyperscaler’s physical buildout. The data-center share was the remaining 35% of its Q3 technical infrastructure investment, according to its October 28 earnings call. Neither percentage measures the supply of rentable GPUs or optical equipment across the market.

Power is a separate clock. EIA’s October outlook estimates that commercial electricity use rose 5% year over year in Q3 2026 and forecasts 2.8% growth in 2027. The commercial category includes data centers and many other users; neither figure measures data-center load. EIA also forecasts 2026 wholesale prices averaging $52/MWh across 11 hubs. Weather and gas prices influence those hub averages; data-center contract prices and project-level delivery costs are different measures.

Connection is not operation. ERCOT’s request seeks information from data-center developers of 25 MW or more who are pursuing interconnection, including on-site generation, water, and cooling. It is an information-gathering step, not proof that a project has connected or secured power.

Financing adds another set of conditions. Lambda’s October announcement describes a fixed-rate loan backed by financed GPU equipment and contracted cash flows. Its coupon cannot be compared directly with unsecured notes or an uncontracted construction loan. SWDI, SpotWire’s proposed fifth monthly index for credit and debt financing, will have no level until a comparable funded cohort and method are ready.

SpotWire collects evidence frequently and publishes interpretation monthly. This briefing summarizes dated primary-source facts and keeps each source’s measurement boundary visible. It makes no claim about an October SpotWire composite value, rental-rate benchmark, or credit rating. Read the methodology or send a correction to press@spotwire.ai.